Ryan P6 Services Pty Ltd

ABN: 83 157 924 224

 

About Us

Capability/Specialising

Services

Contact Us

Careers

 

 

Risk Analysis

All projects carry their own risks, generic and environmental. Our risk management philosophy presents a proactive view of project risk; it is an integral tool in managing projects and business generally. Ryan P6 Services can offer the client strategic and tactical risk management applications - either as part of a broader project management consultancy or as a stand-alone service. We believe a managed risk culture is a key ingredient to project success. We embrace the philosophy that risk management is a fluid process, requiring flexibility and strategic thinking.

Risk is inevitable in a business organization when undertaking projects. However, the project manager needs to ensure that risks are kept to a minimal. Risks can be mainly divided between two types, negative impact risk and positive impact risk. Not all the time would project managers be facing negative impact risks as there are positive impact risks too. Once the risk has been identified, project managers need to come up with a mitigation plan or any other solution to counter attack the risk.

We can plan strategy based on four steps of risk management which prevails in an organization. Let's go through each of the step in project risk management:

Risk Identification

Managers face many difficulties when it comes to identifying and naming the risks that occur when undertaking projects. These risks could be resolved through structured or unstructured brainstorming or strategies. It's important to understand that risks pertaining to the project can only be handled by the project manager and other stakeholders of the project.

Risks, such as operational or business risks will be handled by the relevant teams. The risks that often impact a project are supplier risk, resource risk and budget risk. Supplier risk would refer to risks that can occur in case the supplier is not meeting the timeline to supply the resources required.

Resource risk occurs when the human resource used in the project is not enough or not skilled enough. Budget risk would refer to risks that can occur if the costs are more than what was budgeted.

Risk Quantification

Risks can be evaluated based on quantity. We analyze the likely chances of a risk occurring with the help of a matrix.

Using the matrix, the project manager can categorize the risk into four categories as Low, Medium, High and Critical. The probability of occurrence and the impact on the project are the two parameters used for placing the risk in the matrix categories. As an example, if a risk occurrence is low (probability = 2) and it has the highest impact (impact = 4), the risk can be categorized as 'High'.

Risk Response

When it comes to risk management, it depends on the project manager to choose strategies that will reduce the risk to minimal. We always choose four risk response strategies, which are outlined below.

1.     Risks can be avoided

2.     Pass on the risk

3.     Take corrective measures to reduce the impact of risks

4.     Acknowledge the risk

Risk Monitoring and Control:

Risks can be monitored on a continuous basis to check if any change is made. New risks can be identified through the constant monitoring and assessing mechanisms. Following are the considerations when it comes to risk management process:

Each person involved in the process of planning needs to identify and understand the risks pertaining to the project.

Once the team members have given their list of risks, the risks should be consolidated to a single list in order to remove the duplications.

Assessing the probability and impact of the risks involved with the help of a matrix.

Split the team into subgroups where each group will identify the triggers that lead to project risks.

The teams need to come up with a contingency plan whereby to strategically eliminate the risks involved or identified.

Plan the risk management process. Each person involved in the project is assigned a risk in which he/she looks out for any triggers and then finds a suitable solution for it.

Risk Register

Often project managers will compile a document, which outlines the risks involved and the strategies in place. This document is vital as it provides a huge deal of information.

Risk register will often consists of diagrams to aid the reader as to the types of risks that are dealt by the organization and the course of action taken. The risk register should be freely accessible for all the members of the project team.

Project Risk - an Opportunity or a Threat?

As mentioned above, risks contain two sides. It can be either viewed as a negative element or a positive element. Negative risks can be detrimental factors that can haphazard situations for a project. Therefore, these should be curbed once identified. On the other hand, positive risks can bring about acknowledgements from both the customer and the management. All the risks need to be addressed by the project manager.

Monte Carlo Analysis

Ryan P6 Services complete risk analysis through Monte Carlo software. Monte Carlo Analysis refers to a technique in project management where a manager computes and calculates the total project cost and the project schedule many times. This is done using a set of input values that have been selected after careful deliberation of probability distributions or potential costs or potential durations. The Monte Carlo Analysis is important in project management as it allows a project manager to calculate a probable total cost of a project as well as to find a range or a potential date of completion for the project. Since a Monte Carlo Analysis uses quantified data, this allows project managers to better communicate with senior management, especially when the latter is pushing for impractical project completion dates or unrealistic project costs. Also, this type of an analysis allows the project managers to quantify perils and ambiguities in project schedules.

A Simple Example of the Monte Carlo Analysis

A project manager creates three estimates for the duration of the project: one being the most likely duration, one the worst case scenario and the other being the best case scenario. For each estimate, the project manager consigns the probability of occurrence. The project is one that involves three tasks:

The first task is likely to take three days (70% probability), but it can also be completed in two days or even four days. The probability of it taking two days to complete is 10% and the probability of it taking four days to finish is 20%.

The second task has a 60% probability of taking six days to finish, a 20% probability each of being completed in five days or eight days.

The final task has an 80% probability of being completed in four days, 5% probability of being completed in three days and a 15% probability of being completed in five days.

Using the Monte Carlo Analysis, a series of simulations are done on the project probabilities. The simulation is to run for a thousand odd times, and for each simulation, an end date is noted.  Once the Monte Carlo Analysis is completed, there would be no single project completion date. Instead the project manager has a probability curve depicting the likely dates of completion and the probability of attaining each. Using this probability curve, the project manager informs the senior management of the expected date of completion. The project manager would choose the date with a 90% chance of attaining it. Therefore, it could be said that using the Monte Carlo Analysis, the project has a 90% chance of being completed in X number of days.

Similarly, a project manager can adjudge the estimated budget for a project using probabilities to simulate different end results and in turn use the findings in a probability curve.

How is the Monte Carlo Analysis Carried Out?

The above example was one that contained a mere three tasks. In reality, such projects contain hundreds if not thousands of tasks. Using the Monte Carlo Analysis, a project manager is able to derive a probability curve to show the ambiguity surrounding the duration and the costs surrounding these hundreds or thousands of tasks. Conducting simulations involving hundreds or thousands of tasks is a tedious job to be done manually. Today there is project management scheduling software that can conduct thousands of simulations and offer the project manager different end results in a probability curve.

The Different Types of Probability Distributions/Curves

A Monte Carlo Analysis shows the risk analysis involved in a project through a probability distribution that is a model of possible values.  Some of the commonly used probability distributions or curves for Monte Carlo Analysis include:

The Normal or Bell Curve: In this type of probability curve, the values in the middle are the likeliest to occur.

The Lognormal Curve: Here values are skewed. A Monte Carlo Analysis gives this type of probability distribution for project management in the real estate industry or oil industry.

The Uniform Curve: All instances have an equal chance of occurring. This type of probability distribution is common with manufacturing costs and future sales revenues for a new product.

The Triangular Curve: The project manager enters the minimum, maximum or most likely values. The probability curve, a triangular one, will display values around the most likely option.